We are nearing the finish line! The remaining schedule is:
Oct 27 – Nov 3 – Daily Journal of Commerce advertisement for bids
Nov 4 – pre-bid inspection at the shelterhouse
Nov 12 – bids due
Nov 15 – selected contractor notice to proceed
Dec 31 – project complete