Northgate Pedestrian/Bike Bridge Construction Update – May 2020

The following activities will be taking place over the next several weeks during construction of the Northgate Pedestrian/Bike Bridge:

Northbound I-5 express lane  (nighttime work continues until early June)

Work on the I-5 median, near the northbound I-5 express lane off-ramp at 1st Ave NE and NE 103rd St, will continue this month and into early June.

Nighttime work will take place between 9 PM and 5 AM, starting and ending 2 hours earlier than the regularly scheduled express lane closure hours . During this time, crews will install an underground drilled shaft (see photo of shaft rebar cage below) and will conduct quality assurance testing following construction.

  • Alternate route: Exit 174, NE 130th St/Roosevelt Way NE (one next exit past the closed express lane off-ramp at NE 103rd St)

West side of I-5 (north side of North Seattle College and along N 100th St)

  • Installation of underground drilled shaft structures
  • Quality assurance testing of bridge drilled shaft structures
  • Structural excavation work
  • Preparation of bridge shaft tops for column installation
  • Concrete work on the abutment wall structure:
    • Placing forms and rebar cages (see photo above)
    • Placing concrete
    • Allowing concrete curing time
    • Removing the forms

East side of I-5 (1st Ave NE between NE 100th St and NE 103rd St)

  • Ongoing intermittent lane closures between 7 AM and 3:30 PM, with northbound and southbound traffic maintained
  • Sidewalk demolition
  • Structural excavation
  • Preparation of bridge shaft tops for column installation
  • Retaining wall construction
  • Quality assurance testing of bridge drilled shaft structures
  • Ongoing concrete work for several pier columns:
    • Placing forms and rebar cages
    • Placing concrete
    • Allowing concrete curing time
    • Removing the forms

What to expect during construction

  • Some noise and construction vehicle activity, including cranes
  • Some nighttime and weekend work
  • Detours for people walking and biking
  • Lane reductions on Northgate express lane on- and off-ramp
  • 2 freeway closures and detours (on weekends and at night only)
  • Construction staging and parking impacts near the construction sites, including at the northern side of North Seattle College along N 100th St and on NE 100th St at 1st Ave NE
  • Closure of the North Seattle Park & Ride on 1st Ave NE