The following activities will be taking place over the next several weeks during construction of the Northgate Pedestrian/Bike Bridge:
Northbound I-5 express lane (nighttime work continues until early June)
Work on the I-5 median, near the northbound I-5 express lane off-ramp at 1st Ave NE and NE 103rd St, will continue this month and into early June.
Nighttime work will take place between 9 PM and 5 AM, starting and ending 2 hours earlier than the regularly scheduled express lane closure hours . During this time, crews will install an underground drilled shaft (see photo of shaft rebar cage below) and will conduct quality assurance testing following construction.
- Alternate route: Exit 174, NE 130th St/Roosevelt Way NE (one next exit past the closed express lane off-ramp at NE 103rd St)
West side of I-5 (north side of North Seattle College and along N 100th St)
- Installation of underground drilled shaft structures
- Quality assurance testing of bridge drilled shaft structures
- Structural excavation work
- Preparation of bridge shaft tops for column installation
- Concrete work on the abutment wall structure:
- Placing forms and rebar cages (see photo above)
- Placing concrete
- Allowing concrete curing time
- Removing the forms
East side of I-5 (1st Ave NE between NE 100th St and NE 103rd St)
- Ongoing intermittent lane closures between 7 AM and 3:30 PM, with northbound and southbound traffic maintained
- Sidewalk demolition
- Structural excavation
- Preparation of bridge shaft tops for column installation
- Retaining wall construction
- Quality assurance testing of bridge drilled shaft structures
- Ongoing concrete work for several pier columns:
- Placing forms and rebar cages
- Placing concrete
- Allowing concrete curing time
- Removing the forms
What to expect during construction
- Some noise and construction vehicle activity, including cranes
- Some nighttime and weekend work
- Detours for people walking and biking
- Lane reductions on Northgate express lane on- and off-ramp
- 2 freeway closures and detours (on weekends and at night only)
- Construction staging and parking impacts near the construction sites, including at the northern side of North Seattle College along N 100th St and on NE 100th St at 1st Ave NE
- Closure of the North Seattle Park & Ride on 1st Ave NE